Permit and Inspection Information
All permits are submitted, reviewed, and issued in our portal: https://marathonfl.viewpointcloud.com
- No inspections will be made unless permit card is displayed and visible from the street, and stamped approved plans are readily available.
- The permit will become null and void if the work authorized does not have another approved inspection every one-hundred and eighty (180) days
- Mechanical, electrical and plumbing inspection approvals are required before building inspections.
- Certificate of Occupancy must be secured before this building can be used or inhabited for any purpose.
- Do not remove building permit from job site until issuance of a certificate of occupancy.
All permitted construction must be inspected and you must call or email to schedule your inspection.
At this time all M.E.P Inspections (Mechanical, Electrical & Plumbing) are completed on Mondays, Wednesdays & Fridays Only.
- During normal business hours, please call directly to (305) 289-4133.
- During after hours, please call directly to (305) 743-0033 (select option #4 and then option #1 ).
- Email inspections@ci.marathon.fl.us (at any time)
- Online requests through the portal: https://marathonfl.viewpointcloud.com/dashboard/records.
Inspections received prior to 3:30PM will be scheduled for the next inspection day.
Ensure the following information is included in your request:
1. Permit or Project Number
2. Type of Inspection needed
3. Date the Inspection is to be performed
4. Contractor’s and property owner’s name
5. Address of Job Site
6. Contact person’s Phone Number and Any Special Request
Inspections called in after 3:30 p.m. will be performed within the next two business days.
In order to expedite the inspection, contractors and/or homeowners are asked to ensure that the building is posted with clearly visible numbers for identification.
The Following Inspection Satisfy the 180-Day Requirement
Building
- Auger
- Piling/Pile Caps
- Grade Beams/Slab
- Columns / Tie Beam
- Slab /Wood Floor Stairs
- Roof Trusses/Sheathing
- Framing
- Insulation
- Drywall
Plumbing
- Ground Rough (Per Floor)
- Total Rough (Top Out and Water Pipe)
- Sewer Connection
- Portable Rough
- DWV Rough
- Plumbing Final
Roofing
- Dry-In
- Roofing in Progress
- Roofing Final
Seawall/Dock
- Footings
- Auger Tie Back
- Wall or Cantilever
- Deck
- Davit Bases
- Final
Electrical
- Slab Rough (Per Floor)
- Ground Rough
- Total Rough
- Pool Bonding
- Steel Bonding
- Electrical Final
Mechanical
- A/C Ductwork (Per Floor)
- Rough Mechanical
- Tie Down
- Mechanical Final
Pool/Spas
- Pool Plumbing
- Pool Bonding
- Pool Steel/Anchoring
- Pool Final